If you are working in an older Procore project that is NOT using the ERP version of 'Job to Date Costs', you might notice that the 'Job to Date Costs' column in your project's budget does not match the amounts in your subcontractor progress claims.
Prior to releasing the subcontractor progress claim function, Procore users performed billing with the Draw Requests tool. The Draw Requests tool did not provide project teams with the ability to progress claim variations by line item. When a variation included in a 'draw request' was shown, it was billed as a lump sum amount and as a single line item. When Procore released the Invoicing tool's subcontractor progress claims feature, adding variations to a progress claim required users to bill variations by line item so they would be tied to a cost code. Any existing variations included in a 'draw request' continued to be billed as a lump sum amount and as a single line item.
In Procore's Budget tool, all line items must be associated with a cost code to appear as a line item on a budget. This includes the default 'Job to Date Costs' column, as well as the optional 'Invoices' column. Because some projects had existing variations recorded online items as lump-sum amounts, those variations cannot be included in the. 'Job to Date Costs' column or the 'Invoice' column. This is because the lump sum amount cannot be tied to a cost code.
Your project is affected if any of the following apply:
Your project is not affected if any of the following apply:
It is recommended that you create an additional budget view (see Set up a New Budget View) and remove the 'Job to Date Costs' and 'Invoices' columns. Then assign the new view to the affected projects. Because the following features do not report progress claim values by cost code, you can continue to use the Commitment tool's Summary tab, custom report features and 'Invoices to Date' report.