Delete a CCO Synced with MYOB Advanced Construction
Objective
To delete a Commitment Change Order (CCO) from a Procore project after it has been synced with MYOB Advanced Construction.
Background
After syncing a Procore CCO with MYOB Advanced Construction, users will typically follow the change order process when a CCO needs to be modified. See Create a Commitment Change Order (CCO). On occasion, you might need to delete a synced CCO on a project. Since Procore does not permit users to delete synced commitments, first unlink the records in the two systems. See Unlink CCOs Synced with MYOB Advanced Construction. Once the records are unlinked, you can then delete the commitment in Procore using the steps below.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Commitments tool.
- 'Admin' level permissions on the project's Commitments tool.
- Additional Information:
- When a synced CCO is deleted from Procore, the delete action is captured in the individual item's Change History tab.
- Limitations:
- You cannot delete an 'Approved' change order. See Why can't I edit or delete an approved change order?
- After a synced CCO is unlinked and deleted, the data is permanently removed from the system and cannot be restored.
Prerequisites
Steps
- Navigate to the project's Commitments tool.
Note: Before proceeding, ensure the CCO is unlinked. See Unlink CCOs Synced with MYOB Advanced Construction. - Locate the synced CCO in the list.
- Click View or Edit.
- Update status to Draft.
- Click Save.
- Return to the project's Commitments main tool page.
- Locate the CCO that you wish to delete. Click Delete
.