Unlink a Synced MYOB Advanced Construction Vendor
Objective
To sever the connection between vendor records synced in Procore and MYOB Advanced Construction.
Background
When vendor records are synced between Procore and MYOB Advanced Construction, a connection is created between the two records to ensure any updates you make are synchronized between the two systems. Unlinking a vendor severs a record's connection between two systems. You will no longer be able to sync updates between the systems unless they are linked again.
Things to Consider
- Required User Permissions:
- 'Standard' permission or higher on the company's ERP Integrations tool
- Prerequisites:
- At least one (1) vendor record must be linked between systems. See Link a MYOB Advanced Construction Vendor to a Procore Company.
Steps
- Navigate to the company's ERP Integrations tool.
- Click Vendors.
- Under Filters, click Synced.
- Locate the company/vendor record to unlink.
- Click Unlink.