Update the Percent Complete for a Program Task (iOS)

Objective

To update the Percent Complete field in the project Program tool using an iOS mobile device.

Things to Consider

Prerequisites 

Steps

  1. Navigate to the project Schedule tool using an iOS mobile device.
  2. Tap the program task you want to update. 
  3. Tap Edit
    edit-schedule-item-ios.png
    Note: Percent Complete cannot be updated for Summary program tasks or Milestones.
  4. Enter the current percent complete for the task and tap Done. 
    Note: You can enter a numeric value from 0 to 100. The value enter must be a whole number.
  5. Tap Save.
    save-scheduled-item-ios.png
  6. The program task on the mobile device updates to show the amount you entered for Percent Complete. 
    schedule-item-percent-saved-ios.png
    Note: These changes are also shown in the Program tool on the web application.  