Edit Segment Items on a Project

Objective

To edit segment items in your Project level Work Breakdown Structure (WBS)

Background

segment is a discrete category that an organisation uses to break down its work into manageable components. A segment item is one of many distinct items in a segment. After creating a segment, your company's Procore Administrator can add an unlimited number of segment items to it at the Company level. However, whether or not you are permitted to use the steps below to edit segments at the Project level, depends on the segment's Company level settings. 

 Note

To edit a company level custom segment item that was copied to your project, the Add/Edit/Delete Project Level Segment Items setting must be turned ON by your company's Procore Administrator when adding the segment. To learn more, see Add Custom Segments.

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Admin tool. 
  2. Under 'Project Settings', click the Work Breakdown Structure link. 
  3. In the 'Segments' table, click the segment that you want to work with.

    wbs-segments-add-segment-item.png 
  4. In the 'Segment' table, locate the segment to edit. 
  5. Click in the Description field and type over the existing value with your new one. 
    Example

    In this example, we changed the 'Description' field from "Phase 1" to "Phase I" on a custom segment named 'Phase'. 

    wbs-typeover-description.png

Next Steps

See Also