Create a Budget Modification

 Legacy Content
The Budget Modifications feature is being replaced by a new Budget Changes feature. Starting in October 2022, Procore will be working with Procore customers to migrate from budget modifications to the Budget Changes feature by October 16, 2023. Once you migrate, you will no longer have access to the budget modifications feature. If you have any questions before your company starts the migration, contact your Procore point of contact. To learn more about the timeline for migration, see: Common Questions.

Objective

To transfer money on a locked budget from one budget line item to another using the Budget Modification feature.

Background

The budget modification feature is designed to provide project managers with the ability to accurately adjust a project's current budget. With this feature, you can create modifications that transfer allocated funds between budget line items, which provides you with the flexibility to accurately adjust the budget as allocation amounts change over the course of a construction project. For example, you might want to transfer money from a contingency line item on your budget to cover an unexpected cost from another budget line item. 

 Notes

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Budget tool.  
  2. Determine where you are going to make your budget modifications. Be sure to note the specific cost codes and categories of the affected line items. For example, 02-900; M.
     Note
    If your company is using the ERP Integrations tool, the values in the 'Category' column correspond to the cost types in your integrated ERP system. See Assign Default Cost Types To Cost Codes.

    original-budget-budget-mod.png
  3. Click Create Budget Modifications.
     NoteS

    This button is only visible and available when:

    • The budget is locked. See Lock a Budget.
    • You have 'Standard' level permissions or higher on the project's Budget tool.
  4. Enter details about the funds being transferred: 
    1. From. Select the budget line item from which you want to remove funds. 
    2. To. Select the budget line item to which you want to add funds. 
    3. Transfer Amount. Enter the total amount for the fund transfer. 
    4. Note. Enter a brief, descriptive explanation about the fund transfer. There is no limit on the number of characters you can enter on a note. 
      In the example below, $2000.00 is transferred from the Project Manager cost code and added to the Site manager cost code.
       Notes
      • To automatically perform addition/subtraction or to automatically increase/decrease budget totals, a user with 'Admin' permission on the Budget tool can click the Configure Settings icons-settings-gear.png icon and then place a checkmark in the 'Allow Budget Modifications Which Modify Grand Total' box. 
      • To create multiple budget modifications, click Add Line Item and enter in the cost code divisions and amount. You can create up to seven (7) budget modifications at one time. 

      create-multiple-budget-modifications.png
  5. Click Create.
  6. Changes are highlighted under the "Budget Modifications" column. Related sub-totals will also reflect the changes accordingly. Subtracted amounts are enclosed in parentheses. (e.g. ($2,000.00)) Results from Example 1 are shown below.

    budget-mods.png
     
  7. Remember, you can view the Budget Modifications Report to view a detailed record of all changes including the name of the person who made the change, as well as a timestamp. A link to the report can be found in the right pane of the Budget tool.

    budget-mods-report.png