View a Subcontract

Also available on  ios-gray-icon.jpg  android-gray-icon.jpg

Objective

To view the details of a subcontract in the Commitments tool. 

Background

Depending on the permissions that have been granted, you may be able to view the details of a subcontract. 

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Commitments tool.
  2. Under the Contracts tab, locate the purchase order or subcontract. Then click Edit.

    For companies using the ERP Integrations tool, colour-coded icons and ribbons appear in relevant areas of Procore to show the current status of an item. 

    ICON RIBBON COLOUR DEFINITION
    icon-erp-rejected.png ribbon-erp-rejected.png YELLOW Data that was sent ERP Integrations tool for approval has been retrieved from the tool by an end user.
    OR
    Data that was sent to the ERP Integrations tool has been rejected for export to the integrated ERP system by an accounting approver.
    icon-erp-synced.png ribbon-erp-synced.png GREEN Data is synced between Procore and an integrated ERP system.
    icon-erp-sent.png ribbon-erp-sent.png BLUE Data was sent to the ERP Integrations tool and is waiting for accounting approver to accept it for export to the integrated ERP system. 
    erp-accountant-badge.png   GREEN When a user is designated as an accounting approver, this badge appears next to their user profile in the Company and Project Directory. 
  3. View the subcontract's information by clicking the following tabs:

General Information

  • General Information
    View the basic subcontract information that was entered when creating the subcontract. 
  • Contract Dates
    View important contract dates. 
  • Additional Information
    View contract inclusions and exclusions.
  • Contract Summary Report
    View amounts for the Original Contract, Approved Variations, Revised Contract, Pending Variations,  Draft Variations, Progress Claims, Payments Issued, Percent Paid, and Remaining Outstanding Balance.

Schedule of Values

This tab displays the Schedule of Values for the subcontract, which lists the cost codes, contract amount, billed to date and remaining costs.

commitment-sov.png

Variations

The Variations tab provides an overview of any variations that have been created for that particular subcontract. You can view the status, the amount and the due date for each variation. You can also export each variation to a PDF or CSV. 

 Note
This tab is available to users with 'Admin' permission on the Commitments tool. If you have 'Read-Only' or 'Standard' permission, you must be added as a member of a commitments 'Private' list in order to see it or your company's Procore Administrator must grant you the appropriate granular permission. See Grant Granular Permissions in a Permission Template.


commitment-changeorder.png

RFQs

If the Change Events tool is enabled on the project, this tab displays any Request for Quotes (RFQs) that are related to the subcontract. 


commitments-rfqs.png

Progress Claims

This tab displays any progress claims submitted for that subcontract and outlines the period, billing date, revised contract sum, payment due, retention, balance to finish and percentage complete.

view-invoices.png
 

Payments Issued

This tab displays all payments that have been issued for the subcontract. 
payments-issued.png

Related Items

This tab displays all items related to the subcontract. Related items can be manually added to each subcontract. In this case, the Tender Sheet is automatically listed as a related item because this subcontract was converted to a contract from the Tender Sheet. 


related-items.png

Emails

This tab displays all email communication associated with the subcontract. 

 Note
You will only be able to view this tab if you have 'Admin' level permissions on the Commitments tool or are included in the email.

emailcommitment.png

Change History

The Change History tab outlines changes made to the subcontract, who performed the change, details of the change, from what it was changed from and what it was changed to and the date and time of the change. Items in this history cannot be deleted.

 Note
You can only view this tab if you have 'Admin' level permissions on the Commitments tool. 

change-history.png

Advanced Settings

This tab displays advanced settings that can be configured for the subcontract. 

 Note
You can only view this tab if you have 'Admin' level permissions on the Commitments tool. 


advanced-settings-ciommitments.png

See Also