Mark a Site Diary as Complete
Objective
To mark a Site Diary as complete to verify that the information has been accurately reported and to prevent new entries or modifications from being made.
Things to Consider
- Required User Permissions:
- 'Admin' permissions on the Site Diary tool.
- Prerequisites:
- Additional Information:
- When an Admin marks a Daily Log as Complete, users are prevented from further modifying entries. At any time, an Admin can Re-open the day to make any necessary changes.
- If you want to distribute the completed site diary, there must be users added to the 'Default Distribution' list in the Site Diary tool's configure settings. See Configure Advanced Settings: Site Diary.
- The Programmed Work register pulls live data from the project’s uploaded program and updates automatically.
- If the program changes, even after a day has been marked complete, those updates may be reflected in the log when that day is revisited.
- This ensures the log stays aligned with the most current version of the program.