Skip to main content
Procore Support (en-au)

Create a Head Contract Variation (HCV) with DocuSign®

Objective

To create a Head Contract Variation (HCV) with DocuSign®.

Background

If you have a DocuSign® account, you are able to track the status of a signed document in Procore. You can receive, review and return their signed contracts online, at any time and from any Internet-enabled device.

If you do not have DocuSign® enabled, see Create a HCV from a Change Event or Create a Head Contract Variation (HCV).

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Head Contracts tool.
  • Additional Information:
    • Once you have signed in to DocuSign® through Procore, you will not need to sign in again.  
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  
    • Integration by Procore: Viewpoint® Spectrum®
      • Coming Soon This functionality is coming soon. To sync data:
        • The Date field on a HCV is required.
        • The Billing Item Code on a HCV must be 10 characters or less.
    • Integration by Ryvit: Viewpoint® Vista™
      • This functionality is coming soon.
    • QuickBooks®
      • HCV exports are NOT supported.
    • Sage 100 Contractor®
      • HCV exports are NOT supported.
    • Sage 300 CRE®:
      • Title. The HCV title must be 30 characters or less. 
      • Number (#). The HCV number be five (5) characters or less. 
      • Status. The head contract must be in the Approved status.
      • Associated Line Item. For each line item that you add to the variation's Program of Values (SOV), you may designate one (1) associated line item for each variation line item or the same associated line item for all variation line items.  Note: The Associated Line Item list is only visible and available when the ERP Integrations tool has been configured to work with Sage 300 CRE® and the export head contract variations capability has been switched on in Procore by your Integration Implementation Specialist.

 Prerequisites

Steps

For 2-tier or 3-tier variations or projects not using the Change Events tool

  1. Navigate to the project's Head Contracts tool.
  2. Locate the head contract to work with. Then click its Number link.
  3. Click + Create Head Contract VAR.
  4. Mark the Sign with DocuSign® checkbox.


     
  5. Fill out the related fields. See Create a Head Contract Variation (HCV).
  6. Click Complete with DocuSign® at the bottom of the page. 

  7. If you have not logged into DocuSign® from Procore before, complete the following steps:
    1. Enter your DocuSign® email address.

    2. Click Continue
    3. Enter your password.
    4. Click Register In.
  8. Once you are in DocuSign®, Procore's contract PDF will pre-populate as a document in DocuSign®, or you can choose to add your own document. 
  9. Upload documents by doing one of the following:
    1. Upload
    2. Use a Template
    3. Get From Cloud
  10. If you are not using a custom form, DocuSign® will pre-populate recipient roles. If you choose to use the pre-populated roles, then DocuSign® will pre-place the signing tags in the correct position.

  11. Click Send to send the document for signature. Once the DocuSign® workflow is complete, the variation status will change to "Approved." (If Procore Workflow is not being used). 
    Note: You can still manually edit the variation status if necessary

For 1-tier variations using the Change Events tool

  1. Complete Steps #1-6 in Create a HCV from a Change Event.
  2. Navigate to the change event you created a HCV for.
  3. In the Head VAR section of that change event, click View next to the HCV you want to sign with DocuSign®.
  4. Click Edit.
  5. Mark the Sign with DocuSign® checkbox.
  6. Fill out the related fields. See Create a Head Contract Variation (HCV).
  7. Complete Steps #5-10 above.