Record Changes to Production Quantities in a Prime Potential Change Order

Objective

To add changes to production quantities in a Prime Potential Change Order (Prime PCO).

Background

For companies using Procore's Project Financials and Resource Management tools with the 'Procore Labor Productivity Cost' budget view, you can log additional production quantities associated with a Prime Potential Change Order (PCO) in the 'Production Quantities' tab on the project's Prime Contract's tool. 

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Head Contracts tool. 

Prerequisites

For production quantities to interact with the labour productivity tracking feature, you must:

Steps

  1. Navigate to the project's Prime Contracts tool. 
  2. Locate the Head Potential Variation (Head PV) to work with. 
  3. Ensure that all of the line items that should be associated with the change event have been added. 
  4. Click the Production Quantities tab.
  5. Click Edit.
  6. Click Add Line.
  7. Click Save