Clear an Integrated Program

Objective

To clear an integrated program from the project's Program tool.

Things to Consider

Steps

  1. Navigate to the project's Program tool.
  2. Click the Configure Settings icons-settings-gear.png icon.
  3. Click File Management.
  4. Click the ellipsisicon-ellipsis-vertical.pngicon next to the Upload via Browser button.
    schedule-clear-schedule.png
  5. Click the Clear Program button.
    Note: A confirmation message appears, and you must confirm the deletion to proceed. 
  6. Choose from the following options:
    • To proceed with the delete action, click Clear.
      OR
    • To cancel the delete action, click Cancel