Set Up Submittal Program Calculations

Objective

To set up and use submittal program calculations to automatically calculate date suggestions for approvers' responses. 

Background

Submittal Program Calculations is an optional configuration feature that can be enabled for use with the Project level Submittals tool.  When enabled on a Procore project, this option analyses these key dates, which are entered by the creator under Submittal Program Information in a submittal package or a submittal item:

After analysing the date entries, Procore automatically populates the calculated date values for the end user in the following fields:

Based on the calculated date values above, Procore also suggests dates for the following fields:

This helps the submittal creator ensure that submittal packages and items submitted to the review team are approved on program.

 

Things to Consider

Steps

  1. Follow the steps in Create a Submittal
    This reveals the New Submittal page.
  2. Scroll down to the Submittal Program Information area. 
  3. Set the following information:
    1. Program Task. The program task associated with the submittal being created. A program must be uploaded to the project first. See Upload a Project Program File to Procore's Web Application.
    2. Design Team Review Time. The number of days allotted for the design team's review on the submittal.

      Note: If you enter 7, the system subtracts '7' calendar days from the Planned Return Date to automatically populate the date entry for the Planned Internal Review Completed Date.
    3. Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.

      Note: If you enter 10, the system subtracts '10' calendar days from the Required On-Site Date to automatically populate the date entry for the Planned Return Date.
    4. Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.

    5. Internal Review Time. The number of calendar days that your project's design team requires to ensure the submittal is properly reviewed.

      Note: If you enter 5, the system subtracts '5' calendar days from the Planned Internal Review Completed Date to automatically populate the date entry for the Planned Submit by Date.
      This illustration shows you an example of these entries and calculations.

      create-submittal-schedule-info.png
       

See Also