To add a Daywork Sheet to a change event.
If one or more Daywork Sheet(s) results in a change to a contract's scope of work, you can use the Bulk Actions menu in the Daywork Sheets tool to add a Daywork Sheet to a change event. To perform this action, you will need to have the appropriate permissions on the project's Change Events tool and the Daywork Sheets tool. When you complete this action, Procore automatically links the Daywork Sheets that you selected in the 'Description' field of the selected change event. In addition, any attachments are also linked in the Description and the line item entries on each sheet are added to the change event.
Alternate ways to create change events:
The Daywork Sheet(s) appear as hyperlinks in the 'Description' field of the change event and any attachments in the Daywork Sheet are also included as a link in the Description.