When your company applies the 'Owners English' or 'Specialty Contractors English' point-of-view dictionary, you'll see different tool names and term changes in the user interface. Learn how to apply the dictionary options.
This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials. These dictionaries are available in US English only. The default dictionary is designed for head contractors, which means that you will need to work with your Procore Administrator at your company and your Procore point of contact to access the other dictionary options.
Head Contractors English (United States) - Default |
Owners English (Owner Terminology V2) |
Subcontractors English (Speciality Contractor Terminology) |
---|---|---|
Progress Claiming | Progress Claiming | Progress Billings |
Owner-developer | Funding | Owner-developer |
Owner/Client | Owner/Client | HC/Client |
Head Contract Variation | Funding Variation | Client Contract Variation |
Head Contracts | Funding | Client Contracts |
Revenue | Funding | Revenue |
Subcontract | Contract | Subcontract |
Subcontractor | Contractor | Subcontractor |
Subcontractor Schedule of Values (SSOV) | Contractor Schedule of Values (CSOV) | Subcontractor Schedule of Values (SSOV) |
Billing for stored materials on a construction project allows contractors to recover the costs of purchasing and storing materials on a worksite. It also requires teams to ensure they accurately account for materials received. This includes documenting the trade partners, types of materials, quantities, costs and delivery dates. Because stored materials do not represent completed work, progress claims must be itemized to differentiate between what is installed on a project during a billing period and what is stored for future work.
Once a contractor receives a progress claim payment, stored materials become the client's property and the contractor is responsible for ensuring stored materials are safe. To avoid misunderstandings, ensure the requirements in a project's commitment or head contract are clear about how to bill for stored materials.
To learn how to configure settings and bill for stored materials in Procore, see About Stored Materials on Progress Claims.