When preparing an progress claim in one of Procore's Project Financials tools, the 'Application for Payment' associated with the progress claim shows the 'Current Amount Due' for the billing period. Procore calculates the value in Line '8. Current Payment Due' by subtracting the amount in Line 7. 'Less Previous Certificates for Payment' from Line 6. 'Total Earned Less Retention.'
When viewing an upstream progress claim for a client contract, funding or head contract, the progress claim includes the 'Contractor's Application for Payment' shown below.
In the 'Contractor's Application for Payment' below, the 'Current Amount Due' is calculated as follows:
Line 6 minus Line 7 equals Line 8
$35,421.00 - $7,740.00 = $27,681.30
When viewing a downstream progress claim for a commitment, the progress claim includes a 'Summary Preview' that includes the 'Subcontractor's Application for Payment' shown below.
In the 'Subcontractor's Application for Payment' below, the 'Current Amount Due' is calculated as follows:
Line 6 minus Line 7 equals Line 8
$28,130.00 - $26,339.00 = $1,791.00