What is a budget code in Procore's WBS?

Answer

In Procore's WBS, a budget code is used in Procore's Project Financials tools to keep track of the costs and revenue for a construction project on your financial line items. 

What are the components of a budget code in Procore's WBS?

In Procore's WBS, the components of a budget code are called segments. See What are segments and segment items? Using the Admin tool, your company's Procore Administrator can define which segments are part of a budget code by first defining a budget code structure to use at the company or project level. By default, there are two (2) required segments: cost code and cost type. These are required at both the company and project level. There is also one (1) optional project level segment: sub job. The sub job segment can only be enabled at the project level. See Enable Sub Jobs on Projects for WBS.

Example

in

in


Sub Job *
Sub Job *


Cost Code
Cost Code


Cost Type
Cost Type
[XX]
[XX]
[XXX]
[XXX]
[X]
[X]
Project Admin - Default Budget Code Structure with Optional Sub Job Segment
Project Admin - Default Budget Code Structure with Optional Sub Job Segment
LEGEND
LEGEND
Budget Code Structure
Budget Code Structure
Default Segments
Default Segments
This segment is optional. It can only be enabled on Procore projects.
This segment is optional....
*
*
Text is not SVG - cannot display

What do budget codes look like?

With Procore's WBS, your budget code can be simple or complex, depending upon the number of segments required by your company or project level budget code structure. It really depends upon the type of financial information that you want your teams to capture and track for your organisation and for your organisation's construction projects. To learn more about segments, see What are segments and segment items?

Example

The example below shows you a budget code structure with three (3) segments. Note that the cost code tier is a tiered segment. 


Budget Code
Budget Code


Cost Code (Tier 1)
Cost Code (Tier 1)


[XX…]
[XX…]
Budget Code Structure
Budget Code Structure


Cost Type
Cost Type
[X]
[X]
E - Equiment
E - Equiment
L - Labor
L - Labor
M - Materials
M - Materials
S - Professional Services
S - Professional Services


Program*
Program*
[XXX]
[XXX]
EQP - Equipment
EQP - Equipment
CON - New Construction
CON - New Construction
CNV - Conversions
CNV - Conversions
Cost Code
Cost Code
Program*
Program*
CNV.O.A1-01A
CNV.O.A1-01A
CNV - Conversions
CNV - Conversions
O - Other
O - Other
A1 - Aquisition Costs
A1 - Aquisition Costs
01A - Land
01A - Land
01A - Land
01A - Land
02A - Building
02A - Building
01C - Standard Construction
01C - Standard Construction
1 - Acquisition Costs
1 - Acquisition Costs
D1 - Design Costs
D1 - Design Costs
01B - Standard Construction
01B - Standard Construction
Cost Code (Tier 2)
Cost Code (Tier 2)
LEGEND
LEGEND
Default Segments in Budget Code Structure
Default Segments in Budget Code Structure
Custom Segments in Budget Code Structure
Custom Segments in Budget Code Structure
Your company can choose a custom segment name and add up to (10) custom segments. 
Your company can choose a custom segment...
*
*
Tiered Segment Item in Budget Code
Tiered Segment Item in Budget Code
Available Segment Items in Tiered Segment
Available Segment Items in Tiered Segment
Segment Items Used in Budget Code
Segment Items Used in Budget Code
Segment Items NOT Used in Budget Code
Segment Items NOT Used in Budget Code
Cost Type
Cost Type
RNO - Renovations
RNO - Renovations
O - Other
O - Other
O - Owner Cost
O - Owner Cost

How are segments delimited in WBS?

When creating a budget code, it is also important to note that in the Procore web application's user interface, tiered segments are delimited by a dash (-) and segments are delimited by a period (.). In the example below, the tiered 'Cost Code' segment is 01-904 and each tier is delimited by a dash (-). The next segment in the budget code structure is 'Cost Type' and the period (.) is used as a delimiter to separate it from the cost code. 

Example Budget Code
In Project Financials Tools
Cost Code
Tiered Segment
Cost Type
Flat Segment
budget-code.png 01-904 S=Subcontract

How do I create budget codes?

 Important
First, your company's Procore Administrator must define your company's budget code structure. See Create Your Company's Default Work Breakdown Structure. Next, you must define your budget code structure (you can use your company's default structure or customise one to be project-specific). This step can be performed by a user with 'Admin' level permissions on the Project level Admin tool. See Create Your Project's Work Breakdown Structure.

Once your project's WBS is created, users with the appropriate permissions can then create budget codes in Procore's Project Financials tool. For instructions, see Create Budget Codes for WBS in Procore's Project Financials Tools.

When can I start creating budget codes in Project Financials?

First, your company's Procore Administrator must define your company's budget code structure. Next, a project administrator defines the budget code structure for a project. Once your project's budget code structure is defined, you can begin using Procore's Project Financials tools to create budget codes for the financial line items on your project. See Create Budget Codes for WBS in Procore's Project Financials Tools.

Which Procore tools have a 'Create Budget Code' button? 

The 'Create Budget Code' button is supported in Procore's Project Financials tools. Budget Codes created within project financials tools must use the lowest tier segment available EXCEPT for Budget Codes created in the Head Contracts tool. 

Procore Project Financials Tools Tutorials
Budget
In the Budget tool when creating or editing a budget line item. 
Add a Budget Line Item
Change Events
In the General tab when adding or editing a change event line item. 
Create a Change Event
Variations
In the Schedule of Values on a Commitment Variation, a Head Contract Variation, a Commitment Potential Variation or a Head Contract Variation.
 
Create a Commitment Variation
Create a Head Contract Variation
Create a Potential Variation for a Head Contract
Client Contracts 1
In the Schedule of Values of a client contract.
Create Client Contracts
Commitments
In the Schedule of Values and Subcontractor Schedule of Values on a purchase order or subcontract. 

Create a Purchase Order
Create a Subcontract

Direct Costs
In the Line Items section when creating or editing a direct cost. 
Create a Direct Cost
Funding 2
In the Schedule of Values of a funding.
Create Fundings
Head Contracts 
In the Schedule of Values of a head contract.
Create Head Contracts

Do I need any additional permissions to create budget codes in Project Financials? 

No. To create a budget code, you only need permission to create or edit an item with the corresponding Project Financials tool. For example, to create a budget code while adding a line item to a direct cost, you would need permission to create a direct cost. See Create a Direct Cost. To create a budget code while updating the schedule of values on a head contract, you would need permission to create a head contract. See Create Head Contracts.

 Important

While you can create new budget codes on the fly, the segment items that are part of the budget code must exist in the company level budget code structure. You cannot add new segment items on the fly. Only a Procore Administrator can create a company level budget code structure and only a project administrator can create a project level budget code structure (and only if your company's Procore Administrator has enabled the 'Project Level Actions' settings. See Create Your Company's Default Work Breakdown Structure and Create Your Project's Work Breakdown Structure.

Why can't I import new budget codes into Procore?

With Work Breakdown Structure, the segment items that comprise a budget code must exist in a segment in the company level budget code structure. Instead of importing new budget codes into Procore, your company's Procore Administrator uses the Procore Imports app to import new segment items (for example, cost codes, cost types, sub jobs and custom segments) into your company or project level Work Breakdown Structure. 

See Also