Send a CCO to ERP for Accounting Acceptance
Objective
To send a Commitment Change Order (CCO) to the ERP Integrations tool so it can be accepted by an accounting approver for export to your integrated ERP system.
Background
When you create a CCO on a Procore project, the new CCO must be sent to the ERP Integrations tool in Procore for acceptance by an accounting approver. After acceptance, the system will export the CCO data to your integrated ERP system.
Things to Consider
- Required User Permissions:
- 'Admin' on the project's Commitments tool.
AND - 'Admin' on the project's Change Orders tool
- 'Admin' on the project's Commitments tool.
- Requirements:
- Contract Company. Must be an ERP-linked vendor in the Directory tool.
- Status. Must be 'Approved.'
- Schedule of Values (SOV). Must include at least one (1) line item with an ERP Standard Cost Code.
- Additional considerations and limitations may apply depending on the ERP system your account is integrated with. See Things to know about your ERP Integration for more information.
Steps
- Navigate to the project's Variations tool.
- Click the Commitments tab.
- Locate the desired CCO in the list. Then click View.
- If all the CCO data appears as desired, click Send to ERP.
- The system sends the CCO to the ERP Integrations tool. The following fields are locked and cannot be edited after export:
- Contract Company
- Title
- Status
- Total Amount
- The system sends the CCO to the ERP Integrations tool. The following fields are locked and cannot be edited after export: