Upload Drawing Revisions

Objective

To upload revisions to existing drawings in a project's Drawings tool in Procore.

Background

If you have already uploaded drawings to a project in Procore and need to upload revisions, you will upload them in the same way you would normally upload drawings to the Drawings tool. When you upload drawing revisions to a project, Procore will recognise the drawing number as a duplicate of one you have already uploaded and mark it as a revision of the existing drawing. The drawing revision will automatically appear under the Revision History of the existing drawing.

Things to Consider

Video

 

Steps

  1. Navigate to the project's Drawings tool.
     Note
    An asterisk (*) denotes a required field.
  2. Click Upload Drawings.
    This opens the Upload Drawings prompt. 
  3. Click Attach Files.
     Tip
    For best results, format your drawings for OCR. See How can I improve the accuracy of OCR on my drawings? 
  4. In the Attach Files prompt, click Upload Files
  5. Select the files to upload from your computer or network. 
  6. Once uploaded, click Attach.
    The system returns to the Upload Drawings prompt. 
  7. In the Upload Drawings prompt, click the Select or Create Set drop-down menu under Drawing Set.  
  8. Choose one of these options:

    Select a Drawing Set
    To add the drawing to an existing set: Start typing the set name. Procore shows any sets matching your entry and you can highlight the match to select it. 
    select-drawing-set.png

    Create a Drawing Set
    To add the drawing to a new set: Type a set name and click Create Set [Your Set Name].

    create-drawing-set.png
     
  9. Fill in these fields:
    • Set Date: The date the architect sent the drawing set. 
      • If adding to an existing set, Procore populates this field automatically. 
      • If creating a new set, click the field to select a date from the calendar.
    • Default Drawing Date: The date the drawings were authored. This appears as the 'Drawing Date' on all drawings in the set.
      • Click the field to select a date from the calendar. 
    • Default Received Date: The date a drawing was received or issued by the creator of the drawings (i.e. the design team).
      • Click the field to select a date from the calendar. 
    • Advanced Options: Click the arrow caret-icon.png icon next to Advanced Options to show the following options.

      upload-drawings-advanced-options.png
       
      • Default Revision: If your set has a default drawing revision number or letter, enter it here. The default revision will be set as the 'Revision' for all drawings in this upload.
        Note: If a default revision is not specified, Procore will use the drawing number to determine the revision. 
      • Drawing No. Contains Revision: Click the drop-down menu and select the option that applies to the drawings. If a drawing number contains a revision, the drawing number will be separated at the first decimal or underscore into the Drawing No. and the Revision. For example, a drawing with 'A203.01' would show 'A203' as the Drawing No. and '01' as the Revision. 
        Note: See 'Get From Filename' below for guidelines on filenames if you use both settings.
        • No Rev in Drawing Number: Select if the drawings do not include revisions in the drawing numbers.
        • Rev is After First Decimal: Select if the drawings contain revisions after the first decimal of a drawing number (example: A203.01). 
        • Rev is After First Underscore: Select if the drawings contain revisions after the first underscore of a drawing number (example: A203_01). 
        • Rev is After Last Underscore: Select if the drawings contain revisions after the last underscore of a drawing number (example: A203__EE__01)
      • Drawing Number: 
        • Get From Filename: Mark the checkbox if you want Procore to pull the number and title of an individual drawing based off of the filename. This will bypass OCR and result in higher accuracy in the naming of your drawings.
          Important! If you are using the 'Drawing No. Contains Revision' setting above, drawing filenames should match the following formats:
          • For 'No Rev in Drawing Number': Number_Title.pdf 
            Note: If there is no underscore between the drawing number and title, the entire filename will be entered for the drawing number.
          • For 'Rev is After First Underscore': Number_RevNumber_Title.pdf
          • For 'Rev is After First Decimal': Number.RevNumber_Title.pdf
      • Drawing Language: Procore's OCR can scan for drawings in English, French, German and Spanish. The language for your drawings is automatically selected based on the locale of the project or company, but you can select another language from the drop-down menu if necessary. See Can I change the language that Procore scans my drawings for?
  10. When you are ready to upload the drawings, click Process.
    Note: A progress indicator is shown in the side panel and you will receive a notification email when your upload completes. After the upload has finished processing, you can click Click here to review to review the drawings. review-drawing-files.png

Note:

Next Steps

See Also​