Export the Labour Budget to Actual Report

Objective

To export the project's Labour Budget to Actual Report.

Things to Consider

  • Required User Permissions:
    • 'Read-only' level permission or higher on the project's Reports tool.
      AND
    • 'Read-only' level permission or higher on the project's Timesheets tool.
  • Prerequisites:
  • Supported Export File Formats:
    • Portable Document File (PDF)
    • Comma Separated Values (CSV)

Steps

From the project's Reports tool

  1. Navigate to the project's Reports tool.
  2. Scroll to the Project Reports section.
  3. Click Labour Budget to Actual.
  4. Click Export
    export-labor-budget-to-actual-report.png
  5. Select one of these options:
    • PDF: This exports a copy of the report to the PDF format. 
    • CSV: This exports a copy of the report to a comma-separated values file. 

From the project's Timesheets tool​​​​

  1. Navigate to the project's Timesheets tool.
  2. Click Reports.
  3. Click Labour Budget to Actual.
  4. Click Export
    export-labor-budget-to-actual-report.png
  5. Select one of these options:
    • PDF: This exports a copy of the report to the PDF format. 
    • CSV: This exports a copy of the report to a comma-separated values file.