What are the default columns in the Head Contracts tool?

Answer

By default, the following columns are available in the contracts table in the project's Head Contracts tool. Although you cannot add or remove columns to the table, you can choose to show or hide the columns that display. 

Example

The illustration below shows you the column headings in the project's Head Contracts tool. 

prime-contracts-table-columns.png

Contracts Tab

The table below details the data columns that are available in the Contracts table of the project's Head Contracts tool. 

Column Name Column Format Details
Number Number Shows the contract number.
Owner/Client
OR
BETA GC/Client
Text

Shows the name of the project owner or client. 
OR
BETA Shows the name of the head contractor or client.

Title Text Shows the name entered in Procore for the contract.  
Status - Shows the current status of the contract.
Executed Yes/No Shows whether or not the contract has been executed. 
Original Contract Amount Currency Shows the amount for the original contract. 
Approved Variations Currency Shows the amount of all variations associated with the contract currently in the 'Approved' status.
Revised Contract Amount Currency Shows the revised contract amount after any 'Approved' variations. 
Pending Variations Currency Shows the amount of all variations in the 'Pending' status. 
Draft Variations Currency Shows the amount of all variations in the 'Draft' status.