Skip to main content
Procore

Update the Percent Complete for a Program Task (Android)

Objective

To update the Percent Complete field in the project's Program tool using an Android mobile device.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Project level Program tool.
      OR
    • 'Read Only' or 'Standard' level permissions with the 'Update Task Completion Percentages' granular permission enabled on the permission template.  
  • Additional Information:

Prerequisites 

Steps

  1. Navigate to the project's Schedule tool using an Android mobile device.
  2. Tap the program task you want to update.
  3. Tap Edit.
    edit-schedule-item-android.png
    Note: Percent Complete cannot be updated for Summary program tasks or Milestones.
  4. Enter the current Percent Complete for the task and tap Done.
    save-scheduled-item-android.png
    Note: You can enter a numeric value from 0 to 100. The value you enter must be a whole number. 
  5. Tap Save.
  6. The program task on the mobile device updates to show the amount you entered for Percent Complete.
    Note: These changes are also shown in the Program tool on the web application.
    schedule-item-percent-saved-android.png