Create a Change Event from an RFI (iOS)
Objective
To create a change event from an RFI using the Procore app on an iOS mobile device.
Background
Things to Consider
- Required User Permissions:
- 'Standard' or 'Admin' on the project's Change Events AND RFIs tools.
- Additional Information:
- This asset or item can be viewed or edited in offline mode provided that the asset or item was previously viewed and cached on your mobile device.
Steps
- Navigate to the RFIs tool using the Procore app on an iOS mobile device.
- Tap the RFI you want to create a change event from.
- Tap the ellipsis icon.
- Tap Create Change Event.
- Tap into a field to enter the appropriate information:
- Origin: This field automatically populates with the name of the RFI.
- Title: Provide a title for the change event.
- Status: Select Open, Closed, Pending or Void to indicate the status of the change event.
- Scope: Select TBD, In Scope or Out of Scope to indicate whether the cost is covered in the original contract.
- Type: Select TBD, Allowance, Contingency, Owner Change or Transfer to indicate the type of cost you are preparing for.
- Change Reason: Select a change reason from the drop-down menu.
- Description: Describe the event that may result in a change in costs.
- Add Attachment: To add a photo or file, tap to select from one of the following options:
- Take Photo: This will open your camera application so you can take a photo and directly add it to the item.
- Choose from Library: This will take you to the photos in your device's library. You can then select an image to add to the item.
- Files: This will take you to files that have been saved to your device.
-
- Head Contract (For Markup Estimates): Select a head contract to indicate which head contract’s markup settings should be used to calculate the markup on ROMs.
- Origin: Select one of the project tools to link the item from which the change event originated.
- Tap Create.
- Tap Create.