Add a Change Event Line Item to an Unapproved Head Potential Variation

Objective

To add a change event line item to unapproved potential variation for a head contract.

Background

If the Project level Head Contracts tool is configured with the 2-tier variation configuration setting (see What are the different variation tier settings in Project Financials?), you must perform the Steps below before you can create a head contract variation

 Tip

When do I create a potential variation? Procore recommends creating a potential variation only for any change event line item that is set to 'Out of Scope' and requires your client's or project owner's approval to proceed.

Note: If your project team is using Procore's Request for Quote (RFQ) feature, you can create a potential variation either before or after a response is submitted for an RFQ has been responded to. However, if you wait until after an RFQ response is submitted, Procore automatically populates the potential variation's Schedule of Values (SOV) with data from the RFQ. 

When you create a potential variation, Procore can also be configured to automatically populate its SOV with the Rough Order of Magnitude (Revenue ROM) values. If you choose to hide the Revenue ROM feature, the value depends on the scope assigned to the change event:

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Change Events tool.
  2. Select one or more change event line items. You can select line items from multiple change events.
  3. Click the Bulk Actions menu. Then choose Add to Unapproved Head PCO and select the unapproved head potential variation from the list. 
    add-to-unapproved-prime-pco.png

Procore automatically creates the line items on the potential variation's SOV using the selected change event line items.