To create a head contract variation from a change event.
If the Change Events tool is enabled on your project, your project's variation tier configuration setting (see What are the different variation tier settings in Project Financials?) determines the number of steps leading up to creating a head contract variation:
Are you inviting subcontractors to submit tenders for goods and services using formal RFQs?
If your project team has opted to use the Request for Quote (RFQ) process (see Create RFQs from a Change Event), you do not have to wait until the RFQ is complete to create your head contract variations. However, after invited subcontractors and vendors respond to RFQs and its status is set to 'Pending Final Approval,' Procore does not automatically update the variation's Schedule of Values (SOV) with the appropriate amounts from the RFQ.
To learn more about how the RFQ process affects variations, see What are the different RFQ statuses and how do they affect cost and variation amounts?
Are you using the Revenue ROM function?
If your project team has opted to use the Revenue ROM function, the SOV on your head contract variations is also automatically updated. If you have hidden the Revenue ROM function, any automatic updates depend upon the scope of the change event:
INTERNAL USE ONLY
It is important to be aware of the 'Allow Standard Level Users to Create PCCOs' check box in the 'Configure Settings' page of the Head Contracts tool. This checkbox is enabled by a Superuser setting in the 'General Settings' page of the Company Admin tool named 'Enable Config to Allow Standards to Create CORs, PCCOs, and CCOs'.
Because this setting provides users with 'Standard' level permissions the capability to approve their own changes orders (for example, when the workflow is enabled) in both Head Contracts and the Commitments tool, it is an uncommon setting for Procore customers to implement. By default, this Superuser setting is turned OFF on all new Procore company accounts.
Sign with DocuSign®
If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.
#
Accept the default number, enter a new number, or create a custom numbering scheme for this change order and future ones.
Revision
If you revise a change order later, you can enter the revision number here.
Title
Enter a descriptive name here.
Status
Select the current status of the change order. Procore automatically places the change order in the 'Draft' status. To learn more, see What are the default statuses for change orders in Procore?
Private
Mark this checkbox if you want the item to be private. This means it is only visible to users with 'Admin' level permissions on the contract (or funding).
Due Date
Select a due date to indicate the date by which the 'Designated Reviewer' must approve or reject the change order.
Invoiced Date
Select the date when the change order was invoiced.
Designated Reviewer
Select the Procore user at your organization who is responsible for approving or rejecting the change order. To appear as a selection in this list, the designated reviewer's Procore user account must be added to the Project Directory and have 'Standard' level permissions or higher to the contract or funding tool. See Add a User Account to the Project Directory.
Paid Date
Select the date that payment was received for the change order.
Reviewer
This field is blank on a new change order. After the 'Designated Reviewer' approves or rejects the change order, that person's name appears here.
Review Date
This field is blank on a new change order. After the 'Designated Reviewer' approves or rejects the change order, the date the person submits their response appears here.
Description
Enter a more detailed description of the change order.
Schedule Impact
If this change order is expected to impact the construction project's schedule, enter the estimated number of additional days this would add to the schedule.
Executed
Mark this checkbox after the change order is fully executed.
Potential Change Orders
If the tool is configured for two (2)-tier change orders, select any potential change orders related to this change order from this drop-down list. See Configure the Number of Change Order Tiers on a Project Financials Tool.
Attachments
Add any relevant document or image as a file attachment. You can attach multiple files using these methods: