Configure Advanced Settings: Connection Manager
Objective
To configure settings for the Connection Manager tool.
Background
You can use the settings in the project's Connection Management tool to manage notifications for new project connections, disconnections and connection request activity (if review is required).
Things to Consider
- Required User Permissions
- Only Company Admins or users with 'Admin' level permissions to the Connection Manager tool can be added to receive notifications.
Steps
- Navigate to the project's Connection Manager tool.
- Click the Configure Settings icon.
- Select who should receive notifications.
- All Users with Connection Manager Admin Permissions
Note: This only includes users in the project's Directory. - Specific Users
Note: You can remove users, as well as add users who have Company Admin permissions that have not been added to this project's Directory.- Enter and select the specific users' names.
- All Users with Connection Manager Admin Permissions
- Click Update.