Skip to main content
Procore

Edit a Funding

 Limited Release
flag-us.png The Funding tool is available as a limited release for Procore customers in the United States who have implemented the Procore for Owners point-of-view dictionary. To learn more, see What tool names and terms are different in Procore for general contractors, owners, and specialty contractors?

Objective

To edit a project's funding. 

Background

You can edit the funding's on your project at any time. Once you are ready to move forward, you can edit it to place it into the 'Approved' status.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Funding tool.
  • Additional Information:

Prerequisites

Steps

Edit a Funding

  1. Navigate to the project's Funding tool.
  2. Locate the funding to work with. Then, click its Number link. 
  3. Click Edit
  4. In the General tab, under General Information, modify the following information as needed:
    Notes: There are no required fields when creating a new funding. If you click Create without completing any data entry, the system saves the funding with your name listed as the creator and places it in the Draft status by default.
    • Sign with DocuSign©
      If you are using the Procore + DocuSign© integration (see DocuSign©), a checkmark appears by default. Clear the checkmark from the box if the funding does NOT require a DocuSign© signature. 
    • Funding #
      Accept the default funding number, enter a new number for the funding or create a custom numbering scheme to use.
       Notes
      • If you plan to create multiple fundings, Procore increments this number for you by default. For example; 1, 2, 3 and so on. 
      • To use a custom numbering scheme, you can enter a set of alphanumeric characters (for example, F-1 or F-01 or F-001) and Procore increments the number on new fundings.
    • Title
      Enter a descriptive name for the funding.
    • Owner/Client
      Select the project owner/client from the drop-down list.
    • Architect/Engineer
      Select the lead architect for the project from the drop-down list.
    • Contractor
      Enter the company name of the contractor managing the construction project. If you are setting up the funding, this will typically be your company's name. 
    • Status
      Select the current status for the funding. Options include Draft, Out for Tender, Out for Signature, Approved, Complete or Terminated.
      Note: 
      To create variations and progress claims, a funding's status must be set to Approved or Complete.
    • Executed
      Place a mark in this check box if the funding has been fully executed.
    • Make this Visible Only to Administrators and the Following Users
      Place a mark in this check box to limit visibility to users with 'Admin' permission and any users designated in the 'Allow These Users to See SOV Items' checkbox.
    • Allow These Users to See SOV Items
      Place a mark in this check box. Then select the names of any users who have been granted 'Standard' or 'Read Only' permissions on the Funding tool from the 'Select a Person' drop-down list.
    • Default Retention. Specify a default percentage that will automatically be applied to all line item costs for retention purposes.  For example, enter: 10%
    • Description
      Enter a descriptive summary to provide more detail about the funding.
    • Attachments
      Attach any relevant files to the funding. For example, an electronic copy of the signed funding.
  5. Under Funding Dates, do the following:
     Note
    A user with 'Admin' permission on the Funding tool can configure the tool to show or hide the fields marked with an asterisk (*) below. See  Configure Settings: Funding.
    • Date Created
      Shows the date the funding was created. This cannot be modified.
    • Start Date
      Specify the project's official start date.
    • Estimated Completion Date
      Specify the estimated date for project completion.
    • Substantial Completion Date*
      Select the date from the calendar control. The substantial completion date refers to the date that work is considered sufficiently complete to satisfy legal requirements. It also indicates the date that the tenant can assume occupancy of all or part of a project and you are entitled to receive funding balance payment (less retention) until final completion.
       Note
      If enabled, the substantial completion date will be updated to each Funding Variation's (FCOs) Revised Substantial Completion Date once each FV has a status of Approved.
    • Actual Completion Date
      Select the date from the calendar control. This represents that final payments have been processed and the funding is considered closed.
    • Funding Date*
      Select the date from the calendar control. This represents the effective date of the funding agreement. This is the date the funding goes into force. 
    • Signed Funding Received Date
      Select the date from the calendar control. This represents the date that the executed funding was received.
    • Execution Date*
      Select the date from the calendar control. This represents the date the agreement was signed by all parties. 
    • Issued On Date*
      Select the date from the calendar control. This date represents the date the agreement was issued to both parties.
    • Returned Date
      Select the date from the calendar control. 
    • Letter of Intent Date
      Select the date from the calendar control. A letter of intent date is the date the Letter of Intent (LOI) document outlining the agreement between parties is received before the funding is finalised. 
    • Approval Letter Date*
      Select the date from the calendar control. A letter of approval date is the date that compliance with the fees, statements and disclosures stated in the Letter of Approval (LOA) date that the funding was signed into the record. 
    • Funding Termination Date
      Select the date from the calendar control. A funding termination date is a date outlined in the funding where all parties have met all the obligations and terms.
  6. Under Additional Information, do the following:
    • Inclusions. Specify any agreed-upon inclusions in the funding.
    • Exclusions. Specify any agreed-upon exclusions in the funding.
  7. Click Save.

Add, Delete and Rearrange SOV Line Items 

  1. Navigate to the Funding tool.
  2. Click the Schedule of Values tab.
  3. Click the vertical ellipsis (⋮). Then choose from the following menu options:
    view-prime-contract-sov-options.png
    • Add Above
      Select this option to add a line item above the current line item. 
    • Add Below
      Select this option to add a line item below the current line item. 
    • Delete
      Select this option to delete the current line item. 
       Tip
      To rearrange line items in the list, you can type over the numbers in the # column. This lets you specify the list order of each item on the SOV. 
  4. Click Save.