When your company applies the 'Owners English' or 'Specialty Contractors English' point-of-view dictionary, you'll see different tool names and term changes in the user interface. Learn how to apply the dictionary options.
This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials. These dictionaries are available in US English only. The default dictionary is designed for head contractors, which means that you will need to work with your Procore Administrator at your company and your Procore point of contact to access the other dictionary options.
Head Contractors English (United States) - Default |
Owners English (Owner Terminology V2) |
Subcontractors English (Speciality Contractor Terminology) |
---|---|---|
Progress Claiming | Progress Claiming | Progress Billings |
Owner-developer | Funding | Owner-developer |
Owner/Client | Owner/Client | HC/Client |
Head Contract Variation | Funding Variation | Client Contract Variation |
Head Contracts | Funding | Client Contracts |
Revenue | Funding | Revenue |
Subcontract | Contract | Subcontract |
Subcontractor | Contractor | Subcontractor |
Subcontractor Schedule of Values (SSOV) | Contractor Schedule of Values (CSOV) | Subcontractor Schedule of Values (SSOV) |
Objective
To create a downstream progress claim as an progress claim administrator on behalf of an progress claim contact.
If your company or project doesn't want to grant external collaborators access permission to your Procore project so they can submit their own progress claims, your team can collect the digital or paper progress claims from your progress claim contacts outside of Procore. Once collected, progress claim administrators can create them in Procore on each progress claim contact's behalf.
To perform the Steps in this tutorial, the progress claim's commitment must have:
In addition, a progress claim administrator must create a billing period for the progress claim. See Manage Billing Periods.
Users always create progress claims in the project's Commitments tool.
In the New Progress Claim page, update the General Information card. Once updated, continue by updating the Schedule of Values.
This table details the elements in the 'General Information' card. An progress claim administrator can update this information when creating or editing a progress claim of behalf of an progress claim contact.
Element | Field Type | Description | Learn More | |
---|---|---|---|---|
Contract Company | Read Only | Shows the name of the subcontracting company designated as the 'Contract Company' on the commitment. | To change the company name that appears:
|
|
Status* | Drop-down list | Accept the default status (Draft) or select a different status from the drop-down list.
|
What are the default statuses for Procore progress claims? | |
Progress Claim # | Alphanumeric text | Procore automatically assigns progress claim numbers in sequence using its default numbering system or the custom numbering system defined for your project's progress claims. | Read Can I customise the numbering system for financial objects in Procore? before changing this number. | |
Billing Period* | Drop-down list | Accept the billing period that appears by default or select any billing period from the drop-down list. Note: Progress Claim contacts and users with 'Standard' level permissions on the Commitments tool can only select a billing period when a progress claim is NOT already associated with it. |
Only progress claim administrators can Create Billing Periods. | |
Billing Date* | Calendar control | Shows the billing date for the selected billing period. You can change the date for this progress claim with the calendar control. | Only progress claim administrators can Create Billing Periods. | |
Period Start* | Calendar control | Shows the start date for the selected billing period. You can change the date for this progress claim with the calendar control. | Only progress claim administrators can Create Billing Periods. | |
Period End* | Calendar control | Shows the end date for the selected billing period. You can change the date for this progress claim with the calendar control. Note: To help project managers track how progress claims impact a project's budget, the 'Billing Period' date on a progress claim aligns with the work performed on a project. |
Only progress claim administrators can Create Billing Periods. | |
Billing Type: Progress Billing |
Option button | Requires Procore Pay If the subcontractor is submitting progress billings for an ongoing project, choose this option. |
When your company has Procore Pay, this setting works with the Invoicing Settings for Progress Conditional and Progress Unconditional lien waivers. See Enable Lien Waivers & Set Default Templates on Projects. | |
Billing Type: Final Billing |
Option button | Requires Procore Pay If the subcontractor is submitting a one-time progress claim or if this is the final progress claim for an ongoing project, choose this option. |
When your company has Procore Pay, this setting works with the Invoicing Settings for Final Conditional and Final Unconditional lien waivers. See Enable Lien Waivers & Set Default Templates on Projects. | |
Submitted Date | Calendar control | Select the date the progress claim was submitted to your company by the subcontractor. | Typically, this is printed on the progress claim that you received from the subcontracting company. |
The 'Payment Details' card appears next to the 'General Information card for progress claim administrators with Procore Pay.
To change the payment due date for this progress claim, select a new date from the Payment Due Date calendar.
The data entry fields on a progress claim's Schedule of Values depend on the corresponding commitment's accounting method (Amount Based or Unit/Quantity Based). To learn more, see How do I set the accounting method for a contract?
Click here to view the steps for Amount Based data entry.
For Amount Based commitment contracts, use these steps to update a progress claim's Schedule of Values.
You can alternatively update the Schedule of Values line-by-line. Do this by clicking one or more editable cells and entering your data directly.
Click here to view the steps for Unit/Quantity Based data entry.
For Unit/Quantity Based commitment contracts, use these steps to update a progress claim's Schedule of Values.
You can alternatively update the Schedule of Values line-by-line. Do this by clicking one or more editable cells and entering your data directly.
Click the Save button at the bottom of the 'New Progress Claim' page.
Note: If workflows are turned on for subcontractor progress claims, you can also choose 'Save as Draft' to save your work and stay in the same workflow step.
Optional: If your project team wants to collect signatures on your progress claims using the Procore + DocuSign© integration, click the Send with DocuSign© button at the top of the page. To use this button, the DocuSign© integration must be enabled on the project (see How do I enable the DocuSign® Integration?) and the progress claim must be in the Approved, Approved as Noted or Pending Approval status. To learn more about the DocuSign© integration and preparing envelopes for signature, see DocuSign®.