Delete a Subcontractor Progress Claim from the Commitments Tool (Legacy)
Legacy Content
This content details the Commitment tool's legacy experience. To learn how to use the modernised experience, see Delete a Subcontractor Progress Claim.
Objective
To delete a subcontractor progress claim from a purchase order or subcontract using the project's Commitments tool.
Background
You can use the steps below to delete a subcontractor progress claim from a purchase order or subcontract. Once deleted, the data is permanently removed from Procore and cannot be retrieved.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Commitments tool.
OR - 'Standard' level permissions on the project's Commitments tool and the progress claim must be set to the 'Draft' or 'Revise and Resubmit' status. See What are the default statuses for Procore progress claims?
-
Note
For user with the required user permissions listed above, you can alternatively delete a progress claim from the project's Invoicing tool. For instructions, see Delete a Progress Claim from the Invoicing Tool.
- 'Admin' level permissions on the project's Commitments tool.
- Additional Information:
- You can only delete the most recent progress claim on a commitment.
- Delete actions are recorded in the Change History tab on the commitment.
- Limitations:
- Once deleted, the data is permanently removed from Procore and cannot be retrieved.
-
For companies using the ERP Integrations tool:
- Before you can delete a subcontractor progress claim that has been synced with an integrated ERP system, you will first need to unlink the synced progress claim.
Prerequisites
- You or another user must create a progress claim to delete:
Steps
Choose the following options for deleting a subcontractor progress claim:
- Delete a Progress Claim from the Progress Claims Tab
- Delete a Progress Claim from the Contract's 'Invoice (Commitment progress claim)' Page
Delete a Progress Claim from the Progress Claims Tab
- Navigate to the project's Commitments tool.
- Click the Contracts tab.
- Locate the contract that contains the progress claim you want to delete. Then click its Number link.
This action opens the contract. - In the contract, click the Progress Claims tab.
- Locate the progress claim to delete in the 'Invoices (Commitment progress claims)' section. You can only delete the most recent progress claim on a commitment. Then click the RED (x) icon.
Delete a Progress Claim from the Contract's 'Invoice (Commitment progress claim)' Page
- Navigate to the project's Commitments tool.
- Click the Contracts tab.
- Locate the contract that contains the progress claim you want to delete. You can only delete the most recent progress claim on a commitment. Then click its Number link.
This action opens the contract. - Click the Progress Claims tab.
- In the 'Invoices (Commitment progress claims)' table, locate the progress claim to delete. Then click View or Edit.
This action opens the contract associated with the selected progress claim in the project's Commitments tool. The Summary tab is visible by default.
- Click the Delete button.