The Commitments tool in Procore allows your teams to see the status and current value of all contracts and purchase orders. Easily pinpoint which contracts have been approved or determine the status of progress claims and payments. Procore can be customised to produce your company's contract documents to streamline the process and ensure consistency across projects.

 
 
 
 
 
 
 
 
 
 
  • View and filter a detailed list of all the financial commitments (e.g., contracts, purchase order, etc.) on a project
  • Allow vendors to create and submit their progress claims

There are no items that match your search query.

 
Workflows (BETA)

These tutorials detail the Beta Version of the Workflows tool. To learn more about this release, see About the Workflows Beta Program. See (Beta) Workflows for more tutorials and FAQ's about the company level Workflows tool.

 Tip

To browse and search all Procore training videos, visit our video library.

Web

Configure Commitment Settings - Specialty Contractor
 
Create a Contract - Owner
 
Create a Subcontract - Head Contractor
 
Create a Subcontract - Specialty Contractor
 
Create a Purchase Order
 
Create a Purchase Order - Specialty Contractor
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 
Invite a Subcontractor to Create a Subcontractor SOV - Specialty Contractor
 
Invite a Contractor to Create a Contractor SOV - Owner
 
Edit Subcontractor SOV - Subcontractor as Collaborator
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Invite a Subcontractor to Create a SSOV - Specialty Contractor
 

Owner - Invite a Contractor to Create a Contractor SOV

 

Speciality Contractor as Client - Invite a Subcontractor to Create a SSOV

 

Subcontractor - Edit Subcontractor SOV

 

Speciality Contractor as Client - Create a CV

 

Create and Send Subcontractor Progress Claim Invitations

 

Invite a Subcontractor to Create a SSOV

 

Owner - Create a Commitment Variation

 

Create a CV

 

Speciality Contractor as Client - Configure Commitment Settings

 

Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Create a Contract

 

Speciality Contractor as Client - Create a Purchase Order

 

Speciality Contractor as Client - Create a Subcontract

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create a Subcontract

 

Site Worker - Create a Commitment (Mobile)

 

Commitment Management

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Commitments Configuration

 

Owner - Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Create a Purchase Order

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Site Worker - Create a Commitment (Mobile)

 

Create a CV

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create a Subcontractor Progress Claim on Behalf of Subcontractors

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create and Send Subcontractor Progress Claim Invitations

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Invite a Subcontractor to Create a SSOV

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Create a CV

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create a Subcontractor Progress Claim on Behalf of Subcontractors

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create and Send Subcontractor Progress Claim Invitations

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Invite a Subcontractor to Create a SSOV

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Create a Subcontract - Head Contractor
 
Create a Purchase Order
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Create a Subcontract

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Invite Subcontractor to Create SSOV

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Site Worker - Create a Commitment (Mobile)

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Web

Configure Commitment Settings - Specialty Contractor
 
Create a Contract - Owner
 
Create a Subcontract - Head Contractor
 
Create a Subcontract - Specialty Contractor
 
Create a Purchase Order
 
Create a Purchase Order - Specialty Contractor
 
Invite a Subcontractor to Create a Subcontractor SOV - Head Contractor
 
Invite a Subcontractor to Create a Subcontractor SOV - Specialty Contractor
 
Invite a Contractor to Create a Contractor SOV - Owner
 
Edit Subcontractor SOV - Subcontractor as Collaborator
 

Mobile

Create a Commitment (Mobile) - Field Worker
 

OUTDATED VIDEOS - Removed from Support Site and Certifications

Invite a Subcontractor to Create a SSOV - Specialty Contractor
 

Owner - Invite a Contractor to Create a Contractor SOV

 

Speciality Contractor as Client - Invite a Subcontractor to Create a SSOV

 

Subcontractor - Edit Subcontractor SOV

 

Speciality Contractor as Client - Create a CV

 

Create and Send Subcontractor Progress Claim Invitations

 

Invite a Subcontractor to Create a SSOV

 

Owner - Create a Commitment Variation

 

Create a CV

 

Speciality Contractor as Client - Configure Commitment Settings

 

Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Create a Contract

 

Speciality Contractor as Client - Create a Purchase Order

 

Speciality Contractor as Client - Create a Subcontract

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Create a Subcontract

 

Site Worker - Create a Commitment (Mobile)

 

Commitment Management

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Commitments Configuration

 

Owner - Set Up a Budget

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Owner - Create a Purchase Order

 

Video content may not accurately reflect the current state of the system, and/or it may be out of date.

Commitments

The following table highlights which user permissions are required to perform the described user action.

icon-mindtouch-table-mobile.png: Denotes an action that is supported in Procore's iOS and/or Android mobile application. 

icon-mindtouch-table-check.png+ : Indicates that one or more granular permissions are available for the task. See the relevant tutorial or Grant Granular Permissions in a Project Permissions Template for more information.

erp-integration.png : Indicates your company's Procore account must be configured to work with an integrated ERP system

Task None Read Only Standard Admin
Add a Line Item to a Commitment's Schedule of Values       icon-mindtouch-table-check.png
Add a New Payment to the Payments Issued Tab of a Commitment       icon-mindtouch-table-check.png
Add a Related Item to a Purchase Order or Subcontract (Legacy)       icon-mindtouch-table-check.png
Add a Related Item to a Commitment Variation       icon-mindtouch-table-check.png
Add Financial Markup to Commitment Variations       icon-mindtouch-table-check.png
Add Progress Claim Contacts to a Purchase Order or Subcontract       icon-mindtouch-table-check.png
Add Progress Claim Contacts to a Purchase Order or Subcontract (Legacy)       icon-mindtouch-table-check.png
Allow Collaborators to Submit Site-initiated Variations       icon-mindtouch-table-check.png
Approve and Sign a Subcontract N/A N/A N/A N/A
Change the Privacy Settings for a Commitment   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Complete a Commitment Contract with DocuSign®  2       icon-mindtouch-table-check.png
Complete a Commitment Variation with DocuSign® 2,8       icon-mindtouch-table-check.png
Configure Settings: Commitments       icon-mindtouch-table-check.png
Configure the Default Privacy Settings for New Commitments       icon-mindtouch-table-check.png
Configure the Number of Commitment Variation Tiers       icon-mindtouch-table-check.png
Create a Variation Request for a Commitment      icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create a Commitment Variation       icon-mindtouch-table-check.png
Create a Commitment Potential Variation from a Change Event 9     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create a Purchase Order icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Create a Subcontract   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Create a Subcontractor Progress Claim for the Release of Retention 1     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create a Progress Claim on Behalf of a Progress Claim Contact (Legacy) 3     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Create a Progress Claim on Behalf of a Progress Claim Contact 3     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Delete a Purchase Order or Subcontract       icon-mindtouch-table-check.png
Delete a Commitment Synced with an Integrated ERP System 4 erp-integration.png       icon-mindtouch-table-check.png
Delete a Subcontractor Progress Claim  10     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Edit a Purchase Order (Legacy) 7 icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Edit a Subcontract (Legacy) 7 icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Edit a Commitment Synced with an Integrated ERP System erp-integration.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Edit the Advanced Settings Tab on a Commitment       icon-mindtouch-table-check.png
Email a Commitment      icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Enable Financial Markup on a Commitment       icon-mindtouch-table-check.png
Enable or Disable the Subcontractor SOV Tab on a Commitment       icon-mindtouch-table-check.png
Enable or Disable the Subcontractor SOV Tab on the Commitments Tool       icon-mindtouch-table-check.png
Enable the Payments Issued Tab on a Commitment       icon-mindtouch-table-check.png
Enable Retention on a Commitment   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Enable Sliding Scale Retention Rules on a Commitment's Progress Claims       icon-mindtouch-table-check.png
Enable the Payments Issued Tab on a Commitment       icon-mindtouch-table-check.png
Export a Commitment Variation to an Integrated ERP System erp-integration.png       icon-mindtouch-table-check.png
Export a Commitment to an Integrated ERP System erp-integration.png       icon-mindtouch-table-check.png
Export a Commitment 5   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Export a Commitments List 7   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Export a Payment Program       icon-mindtouch-table-check.png
Import Commitment SOV Line Items from a CSV File   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
Request to Reset a Commitment Synced with an Integrated ERP System erp-integration.png       icon-mindtouch-table-check.png
Review a Subcontractor SOV for a Commitment       icon-mindtouch-table-check.png
Review Progress Claims as a Subcontractor 1     icon-mindtouch-table-check.png  
Review Subcontractor Progress Claims as an Admin       icon-mindtouch-table-check.png
Retrieve a Commitment from ERP       icon-mindtouch-table-check.png
Search for and Apply Filters to Commitments icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Send a Commitment Variation to ERP Integrations for Accounting Acceptance erp-integration.png       icon-mindtouch-table-check.png
Send a Commitment to ERP Integrations for Accounting Acceptance erp-integration.png       icon-mindtouch-table-check.png
Set or Release Retention on a Subcontractor Progress Claim 3     icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Submit a Site-initiated Variation as a Collaborator   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+  
Submit a New Progress Claim as a Progress Claim Contact 3   icon-mindtouch-table-check.png icon-mindtouch-table-check.png icon-mindtouch-table-check.png
Update a Subcontractor Schedule of Values as a Progress Claim Contact from the Invoicing Tool  1, 6   icon-mindtouch-table-check.png icon-mindtouch-table-check.png  
View a Purchase Order 7 icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
View a Subcontract 7 icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
View Inclusions/Exclusions for Subcontracts icon-mindtouch-table-mobile.png   icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png+ icon-mindtouch-table-check.png
View the Change History of a Commitment       icon-mindtouch-table-check.png

1 To perform this task, downstream collaborators should be designated as a progress claim contact on the commitment. See Add Progress Claim Contacts to a Commitment

2 Also requires a DocuSign© account.

3  Users must have 'Read-Only' or 'Standard' permissions on the project's Commitments tool. Users must also be added to the Private drop-down list for that commitment or must be designated as a Progress Claim Contact. See Add Progress Claim Contacts to a Purchase Order or Subcontract

4 Commitments synced with an integrated ERP system cannot be deleted until they are unlinked. See Delete a Commitment Synced with QuickBooks® Desktop and Delete a Commitment Synced with Sage 300 CRE®.  

5 Users with 'Admin' permissions on the project's Commitments tool can export a commitment as either a PDF or a DOCX file. Users with 'Standard' or 'Read-Only' permissions on the project's Commitments tool can export a commitment to the PDF file format if they have been granted access to the purchase order or subcontract via the Private drop-down list and the 'Allow These Users to See SOV Items' check box is enabled.

6 Users with 'Read-Only' permissions on the Commitments tool can perform these procedures if they are also listed in the Private field under the commitment's General tab.

7 Users with 'Read only' and 'Standard' permission (and who have NOT been assigned the granular permission detailed in the table) must also be a member of the 'Private' list. 

8 Also requires 'Standard' or 'Admin' permission on the project's Change Events tool.

9 Users with 'Standard' level permissions on the project's Commitments tool can create PVs when they are added to the 'Private' drop-down list and the 'Allow Standard Level Users to Create PVs' configuration must be selected.

10 The progress claim must be in the 'Draft' or 'Revise and Resubmit' status for a user with 'Standard' level permissions to delete it.

 

Below are the notable changes to the project's Commitments tool. 

Recent Changes

FINANCIAL MANAGEMENT: NEW WARNING BANNER ON SUBCONTRACTOR INVOICES WHEN RETENTION IS RELEASED (24/04/2023)

Subcontractor progress claims have a new warning banner that will appear when retention is released. The banner will appear from the Schedule of Values (SOV) card once retention amount is entered and released. See Set or Release Retention on a Subcontractor Progress Claim.

FINANCIAL MANAGEMENT: Extended The Legacy Subcontractor Progress Claim Experience Date (26/01/2023) 

The option to switch between the beta and legacy subcontractor progress claim experience has been extended to September 2023. The previously announced end date for using the legacy experience was February 2023. Now, in September 2023, the ability to exit the beta experience will be removed and the legacy experience will no longer be available in Procore. To learn more about each experience, see Financial Management: New Admin & Collaborator Views for Subcontractor Invoicing.

Custom Fields now visible in commitments List view (05/01/2023) 

Users can now see custom fields in the commitments list view table. Users can now view, filter and sort by custom fields in the list view.