How do I set and release retention on a subcontractor progress claim in Procore?
Background
Answer
The practice of setting and releasing retention on progress claims protects contractors from potential losses and helps to ensure quality work by subcontractors. To set or release retention on a subcontractor progress claim, you must be an progress claim administrator.
Set Retention
To set retention on one (1) or more line items in a subcontractor progress claim's schedule of values:
- Navigate to the Invoicing tool.
- Click the Subcontractor tab.
- Find the subcontractor progress claim to edit.
- Click the Progress Claim # link to open it.
Tip
Alternatively, you can navigate to the Commitments tool, open the desired commitment and then click the Progress Claims tab. Then, click the Progress Claim # link to open it. - Scroll to the progress claim's Schedule of Values.
- Click Edit.
- Mark one (1) or more line item checkboxes and click the Edit Values button.
This opens the Edit Values panel. - Enter a value in the Work Retention this Period (%) box to set the amount to withhold on the selected line items.
- Click Apply.
Example
For example, to withhold 10% retention on the first progress claim's selected line items, type 10 in the Work Retention This Period (%) box in the Edit Values panel. After clicking Apply:
- The first line item has a Total Completed & Stored to Date Value ($) of $500.00 USD. Procore calculates the amount to withhold to update the Work Retention this Period ($) value to $50.00 USD.
- The second line item has a Total Completed & Stored to Date Value ($) of $2,096.25 USD. Procore calculates the amount to withhold to update the Work Retention this Period ($) value as $209.63 USD.
Procore updates the Total Retention column on the far right of each line item to show the total retention amount the line item on this progress claim. The system also updates the Total Retention column's subtotal row, as well as the Retention total the bottom of the progress claim. In this example, the amounts withheld for each line item are $50.00 USD and $209.63 USD for a Retention total of $259.63 USD on the progress claim.
Release Retention
To release retention on one (1) or more line items in a subcontractor progress claim's schedule of values:
- Navigate to the Invoicing tool.
- Click the Subcontractor tab.
- Find the subcontractor progress claim to edit.
- Click the Progress Claim # link to open it.
- Scroll to the progress claim's Schedule of Values.
- Click Edit.
- Mark one (1) or more line item checkboxes and click the Edit Values button.
- Enter a value in the Retention Released (%) box to set the amount of retention to release for the selected line items.
- Click Apply.
Example
When creating a new progress claim for the commitment in the next billing period, note that Procore automatically inputs some of the previous progress claim's data on the new progress claim.
For this example, the subcontractor has completed 100% of their work, so 100% of the retention withheld on the previous progress claim will be released. To release 100% of the retention, type 100 in the Total Completed & Stored to Date (%) box in the Edit Values panel. After clicking Apply, Procore updates the highlighted values to release 100% of the retention withheld on the previous progress claim or $259.63 USD.