Skip to main content
Procore

Clear an Integrated Program

Objective

To clear an integrated program from the project's Program tool.

Things to Consider

  • Required User Permissions:
    • 'Admin' on the project's Program tool. 
  • Additional Information:
    • When you clear a program from the Program tool, you are removing the integrated program from the project. However, any calendar items that were manually created under the Program tool using Procore's Program tool will not be deleted when you clear the program.

Steps

  1. Navigate to the project's Program tool.
  2. Click the Configure Settings icons-settings-gear.png icon.
  3. Click File Management.
  4. Click the ellipsisicon-ellipsis-vertical.pngicon next to the Upload via Browser button.
    schedule-clear-schedule.png
  5. Click the Clear Program button.
    Note: A confirmation message appears, and you must confirm the deletion to proceed. 
  6. Choose from the following options:
    • To proceed with the delete action, click Clear.
      OR
    • To cancel the delete action, click Cancel