Variations and Change Events
Expedite Projects - Project Managers Procore Training
- Procore > Select project > Tools > Change events
- Procore's way of managing the change before something becomes a variation because some change events don't become variations
- Click Create - fill out.
- Title, status (open), origin (source), type, reason, scope, head contract for markup estimates (automatic)
- Attach any documents
- Add line > add budget code, description, vendor, unit of measure (ls), Add in the Unit costs and Quantity as 1 for Revenue/Cost/Budget.
- If there's a PO for it, add in the contract
- Click create
- Optional: Select change evens, click send requests for quote (RFQ)
- Select the change event - add to Head contract PV.
- HC PV - New Head PV - Contracts - Project's Contract
- Might want to create a Head Contract called Variations?
- Takes you to New Potential Variation
- Auto populates, change Status to Approved, and HC Variation to Create New
- Click Create
- VO is found under contract number in head contracts tool
- Create Head Contract VAR to the Potential variation
- Title, claim date, due date, add potential variation, click create
- Commitment - Add to PO - New Purchase Order or Subcontract
- Fill in, then click create.
- Company, status to approved, dates?
- VO is found in Contracts tab under Commitments tool