Create a Head PV from a Change Event
Objective
To create a potential variation for a head contract from a change event.
Background
If your company has configured your project to use a two (2) tier variation structure, the change event process requires you to create a potential variation. Then, you will create the HCV from the Head Contract tool. When you create a PV, the Schedule of Values (SOV) will populate with the Latest Price values.
Things to Consider
- Required User Permissions:
- 'Standard' level permissions or higher on the project's Change Events tool.
AND - 'Standard' level permissions on the project's Head Contracts tool and the 'Allow Standard Level Users to Create PVs' configuration setting must be enabled on the Head Contracts tool. See Configure Settings: Head Contracts.
- 'Standard' level permissions or higher on the project's Change Events tool.
- Additional Information:
- Depending on the variation tier configuration setting configured for the Head Contracts tool, potential variations can be transitioned into one (1) of the following items:
- For two (2) tier variations, a head contract variation.
- For three (3) tier variations, a variation request.
- To learn more see, What are the different variation tier settings in Project Financials?
- Depending on the variation tier configuration setting configured for the Head Contracts tool, potential variations can be transitioned into one (1) of the following items:
Prerequisites
- The Change Events tool must be turned ON on the project. See Add and Remove Project Tools.
- The two (2) tier variation configuration settings must be turned ON the Head Contracts tool. See Configure the Number of Head Contract Variation Tiers.
- The project's head contract must be in the 'Approved' status. See Approve a Head Contract.
Steps
- Navigate to the project's Change Events tool.
- In the table, mark the checkboxes for one (1) or more change event line item(s) to include in the new potential variation.
Note
Procore creates the potential variation's Schedule of Values (SOV) using the selected change event line item(s). - Click the Bulk Actions menu and choose the Create Head PV option. Then choose the appropriate contract option from the sub menu.
- In the 'New Potential Variation' page, complete the following data entry:
-
Note
If the Request for Quote (RFQ) feature is turned ON, you can configure the Change Events tool to include any attachments added to a reviewer's RFQ response. For instructions, see Configure Settings: Change Events.
- Click Create.
Notes
- The Associated Line Item drop-down list only appears if your company's Procore account is integrated with an integrated ERP system and the Head Contracts tool is active on the project.
- When adding line items to the variation's schedule of values, you must select an Associated Line Item for each new line item. You can designate one (1) associated line item or use the same associated line item for multiple line items. Choosing to create a new line item to associate will automatically create a new zero (0) dollar line item on the contract's original SOV.