Objective
To create Inspection entries in the project's Site Diary tool.
Background
The Inspections section tracks inspections made by third-party inspectors that occur throughout the project. Use this section if you do not have Inspections on your project.
Things to Consider
- Required User Permissions:
- 'Standard' or 'Admin' level permissions on the project's Site Diary tool.
Steps
- Navigate to the project's Site Diary tool.
- Scroll to the Inspection section.
- Enter the following information:
-
#: This uneditable field counts the number of entries in a section (e.g. the first entry created will be # 1, and the second entry will be # 2).
-
Register Date: This field specifies the date that the site diary entry applies to. This field will only display when viewing multiple days in the Site Diary tool and is uneditable.
-
Start: Enter the starting time by selecting the hours and minutes from the drop-down menus.
-
End: Enter the ending time by selecting the hours and minutes from the drop-down menus.
-
Inspection Type: Enter the type of inspection that was performed.
-
Inspecting Entity: Enter the type of inspector that performed the inspection.
-
Inspector Name: Enter the name of the person who performed the inspection.
-
-
Area: (Optional) Enter the area within the specified location that was inspected.
-
Comments: Enter any comments that may be needed to further describe the entry.
-
Attachments: Attach any additional files to the entry. Click Attach File(s) and then drag-and-drop a file from your computer to the Drag and Drop your File(s) area or click Upload Files to select a file from your computer. Once you save your item, users will be able to view the attachment in Procore's viewer or download the attachment.
- Click Create.