flag-us.png flag-canada.png The Progress Billings tool is only available to Procore customers in the United States and Canada who have implemented the Procore for Speciality Contractors point-of-view dictionary. To learn more, see (Limited Release) Owners & Speciality Contractors Point-of-View Dictionary Options

Objective

To learn how to edit the 'Configurable PDF' tab for a HC/Client progress claim in the Progress Billings tool.

Background

This tutorial shows you how to use the options in the Configurable PDF tab of a HC/Client progress claim. You can use the options in this tab to customise the way line items are displayed on the PDF, such as how you want to group and summarise progress claim line items so they display the way you want before you present the PDF to your head contractor or client. 

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Client Contracts tool.
       Note
      Your ability to perform tasks with the Progress Billings tool depends on the permissions you've been granted on the contract or commitment that you are working with. To learn more about the specific tasks that you can perform with the Progress Billings tool, see Permissions: Progress Billings.
  • Additional Information:
    • If you click the Email Progress Claim button, only the Detail tab PDF of the Progress Claim will be sent to recipients, not the 'Configurable PDF' tab.

Steps

  1. Navigate to the project's Progess Billings tool.
  2. Click the HC/Client tab. 
  3. Locate the progress claim to work with. Then click its Progress Claim # link. 
  4. Click the Configurable PDF tab.
  5. Edit the PDF in any of the following ways:
    1. Summarization
      By clicking the arrows, you can expand and collapse the line items to show differing levels of data. To expand, click the arrow illustrated below. To collapse, click the arrow again. 
      gc-client-configurable-pdf-summarization.png
    2. Grouping
      Click the Group drop-down list to the group or subtotal line items by your selection:
      add-groups-manage-custom-groups.png
      • Optional: Sub Job
        This option is only available if the sub job feature is active on the project. See Enable Sub Jobs on Projects for WBS and Add 'Sub Job' Segment Items to a Procore Project.
      • Cost Code Tier 1. If your cost code structure is tiered, this option groups data by the first tier.
         Note
        For Procore project's using Procore's default cost codes that align with the CSI MasterFormat, the 'Division' concept is equivalent to the 'Cost Code Tier 1' option. If you want to group your data by 'Division', select the 'Cost Code Tier 1' option. 
      • Cost Code Tier 2. If your cost code structure is tiered, this option groups data by the second tier in your structure.
      • Cost Type. This option lets you group data by your company's 'Cost Type' segment. For details, see What are Procore's default cost types?