Variations
- Variation to a commitment = Commitment > Create > Create change event > Title > scroll down to Add line >
- Insert: Budget code, vendor, contract.
- If it's just to change the budget and commitment, then insert the amounts in 'Cost' and 'Budget', but not revenue. It will automatically put in a revenue number, so delete them before you click Create.
- If you need to change the revenue as well, enter the revenue amount in 'Revenue.'
- Click Create > Select the box beside the row you've just created and click Add to Commitment VAR > New Commitment VAR > Contracts with matching cost codes > Select the commitment.
- Change status to approved > Scroll down and click Create.
- To change the budget, scroll down and click View > Select the box > Add to > New budget change > Change status to Approve.
- Variation to a Head Contract = Head Contract > Create > Create change event > Title > scroll down to Add line > Insert budget code >
- If it's just to change the revenue, then just insert the numbers in 'Revenue.'
- If it's to change the budget and commitment too, then insert the amounts in 'Cost' and 'Budget' and add a vendor and contract if applicable.
- Click Create > Select the box beside the row you've just created and click Add to Head Contract PV > New Head PV > Contracts with matching cost codes > Select the contract.
- Change status to approved > Scroll down and click Create.
- Then the variation will show up in the Head Contract > Create a progress claim and input the amount in the variation line item.