Skip to main content
Procore

Record Changes to Production Quantities in a Change Event

Objective

To add changes to production quantities in a change event.

Background

For companies using Procore's Project Financials and Workforce Management tools with the 'Procore Labour Productivity Cost' budget view, you can log additional production quantities and production hours associated with your change event line items in the 'Production Quantities' section of a change event. 

Example

Let's assume that after your project's budget is locked, the project owner requests a design change that is out of scope with the original design. The change requires additional drywall, so you first create a change event and add a line item to that change event for that drywall. If that change represents a change to production, you will also want to record that change in the 'Production Quantities' tab of the change event.

Once you record the production quantities in the change events, the values are updated in the Change Events view page. The production quantities may also be associated with any Head potential variation or Budget Change created from a Change Event. However, you must follow these steps: Create a Head Potential Variation from a Change Event

After you have submitted your head contract variation to the owner for review, the owner can then approve or reject it. See Approve or Reject Head Contract Variations. When the status of the head contract variation changes to 'Approved', the updated production quantities are reflected in the 'Procore Labour Productivity Cost' budget view and the Field Production Report. 

Things to Consider

  • Required User Permissions:
    • 'Standard' level permissions or higher on the project's Change Events tool. 

Prerequisites

For production quantities to interact with labour productivity tracking feature, you must:

Steps

Production Quantities relate to contracts and the budget through a combination of sub job and cost code. Users may edit these fields when editing change events line items in the change events edit page. However, if the Production Quantities are associated with a Head potential variation or Budget Change, the Production Quantity will be locked unless unlinked from the change objects.

  1. Navigate to the project's Change Events tool. 
  2. Locate and open an existing change event in the Line Items tab.
    OR
    Create a new change event. See Create Change Events
  3. Scroll to the Production Quantities card.
  4. Click Add Line.
  5. Complete the line item data entry as follows:
  6. Click Save