Add a New Payment to the Payments Issued Tab of the Invoicing Tool
Objective
To add a payment to the Payments Issued tab of a commitment from the Invoicing tool.
Background
To keep track of any payments that your company issues for subcontractor progress claims, you can use the steps below to add a payment record to the Payments Issued tab on a commitment.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Commitments tool.
Prerequisites
Steps
Open the Progress Claim's Commitment
- Navigate to the project's Invoicing tool.
- Click the Subcontractor tab.
- Locate the progress claim that you want to issue a payment for.
- Click the link in the progress claim's Commitment column to open that commitment.
Add a Payment to the Commitment
- In the commitment, click the Payments Issued tab.
- Click Edit.
- In the Add Payment window, enter the following:
- Progress Claim
Select an existing progress claim from the drop-down that the issued payment is attached to.
Note: If the payment is linked to the progress claim, the Payment Status column on the Billings page will update from Unpaid to either Partially Paid or Paid for that progress claim's billing period only. - Payment #
Enter the related payment number for the issued payment. - Payment Method
Select a payment method from the drop-down list: Check, Credit Card, and Electronic. - Amount
Enter the amount of the payment. - Date
Enter the issue date for the payment - Progress Claim #
Enter the related progress claim number for the payment issued. - Check #
Enter the related check number for the payment issued. - Notes
Enter any additional notes regarding the issued payment for record purposes. - Attachments
Attach any relevant files or documents.
- Progress Claim
- Click Add.