Skip to main content
Procore

Create Head Contract Progress Claim (Beta)

 In Beta
This page details the modernised owner progress claim experience.

Objective

To generate an owner progress claim to bill an upstream collaborator for work on a head contract.

Background

When managing your construction project in Procore, you can generate an owner progress claim to bill an upstream collaborator on a head contract. Then, submit the progress claim as a payment application

 Tip

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Head Contracts tool.
  2. Find the contract for which you want to generate a progress claim. 
  3. In the Number column, click the link to open it.
    prime-contracts-number.png
  4. In the contract, click the Progress Claims tab. 

    prime-contracts-invoices-tab.png
     
  5. Click + Create and choose Create Progress Claim from the drop-down menu. 
     Tip
    Is the menu option greyed out? To activate this option, place the contract into the Approved or Complete status. 
    prime-contracts-create-invoice-menu.png

    This opens the 'New Progress Claim for [Contract]' page.
  6. In the Create Progress Claim card, do the following:
     Note
    An asterisk (*) below indicates the field is required. 
    • Progress Claim No.
      Enter a progress claim number or leave it blank and edit later.
    • Billing Period
      Procore selects the open billing period's date range or, if no open period, the most recent period's date range.
       Tip

      How do you create a billing period? Only an progress claim administrator can create billing periods with the Invoicing or Progress Billings tool. See Create Billing Periods

    • Populate the Schedule of Values with Costs from the Selected Billing Period
      Mark this checkbox to turn the setting ON or remove the checkmark to turn the setting OFF. By default, this setting is turned OFF. 
      • ON. Procore populates the progress claim's schedule of values with eligible cost amounts from the selected billing period as follows:
        • Subcontractor progress claims in any Approved status. See What are the default statuses for Procore progress claims?
        • Direct costs with a 'Received Date' in the Approved status with a corresponding budget code in the contract's or funding's Schedule of Values
        • Commitment variations in the Approved status with a corresponding variation or a corresponding budget code in the commitment's schedule of values. 
           Notes

          If the following is true about a commitment variation, Procore automatically populates the data to the progress claim's schedule of values: 

          • It is connected to a head contract variation via a change event, the data populates the head contract variation.
          • It is NOT tied to a head contract variation, the data populates the head contract's Schedule of Values line item with a matching budget code.

          If a variation does not meet the criteria above, Procore will NOT populate the data in the schedule of values. 

      • OFF. Procore does NOT populate the Schedule of Values with costs. Users must manually enter the data in the schedule of values. 
    • Include backup from direct costs and progress claims in the selected billing period
      Mark this checkbox to turn the setting ON or remove the checkmark to turn the setting OFF. By default, this setting is turned ON. 
      • ON.  Updates the progress claim's Attachments card in the progress claim to contain these sections: Uploaded Attachments, Attachments from Subcontractor Progress Claims, and Attachments from Direct Costs. Procore adds the relevant attachments from the selected billing period as follows:
      • OFF. Only the Uploaded Attachments card and button are available. 
  7. Click Create.
    Procore creates the progress claim. Continue the next step.

    See Also