Create an Owner Progress Claim (Legacy)
Objective
To create an owner progress claim to bill an owner for work completed on a head contract.
Background
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Head Contracts tool.
Notes
- To view the Detail tab on an owner progress claim, 'Read Only' or 'Standard' level permissions on the project's Head Contracts tool with the 'View Owner Progress Claim Detail' granular permission enabled on your permission template.
- To learn how to view contracts, see View a Head Contract.
- 'Admin' level permissions on the project's Head Contracts tool.
- Additional Information:
- When you enter a value for a progress claim that is larger than the programd value, the progress claim is highlighted in RED.
- You can only edit the billed amounts on the most recent progress claim.
- To learn how amounts are automatically completed by Procore on head contract progress claim, see How does Procore automatically fill in amounts on an upstream progress claim?
Prerequisites
- Create a head contract. See Create Head Contracts.
- Place the head contract in the 'Approved' or 'Complete' status. See Approve a Head Contract.
- Create a billing period. See Manage Billing Periods.
Steps
- Create the Progress Claim
- Edit the Progress Claim Line Items on the Detail Tab
- Add Approved Variations to the Progress Claim
- Save the Progress Claim
Create the Progress Claim
- Navigate to the project's Head Contracts tool.
- Locate the contract to work with. Then click its Number link.
- Click the Create Progress Claim button.
Note
If you've already created the progress claim for current billing period, click the Progress Claims tab. Next, click the Edit button to open it. - In the 'New Progress Claim (Payment Application)' page, do the following:
- Commitment Billing Period
Select the current billing period from the drop-down list. To learn how to create a billing period, see Create Billing Periods. - Progress Claim #
Procore automatically assigns progress claim numbers in ascending numerical order, starting with one (1). The number entered in this field does NOT affect Procore's default progress claim numbering scheme and you can change it as you want. - Period Start
Procore automatically populates this field with the selected billing period's start date. - Period End
Procore automatically populates this field with the selected billing period's end date. - Billing Date
Click the calendar control and choose a billing date for the progress claim. - Status
Procore automatically places the progress claim in the 'Draft' status. Select a different status from the drop-down list. See What are the default statuses for Procore progress claims? - Percent Complete
If previous progress claims exist, this field shows the percentage of work completed. - Attachments
Click Attach Files or drag-and-drop any files to associated with the progress claim in the attachments area.
- Commitment Billing Period
- Click the Create button.
- In the Do You Want to Pre-Fill the Owner Progress Claim? message, review the list of items that Procore will add to the progress claim and compile a progress claim backup from. Choose one (1) of these options to proceed:
- Cancel. Click this button to cancel progress claim creation.
- No Thanks. Click this button if you want to manually perform the data entry on the progress claim.
- Yes. Click this button to allow Procore to automatically complete the progress claim amounts as described in How does Procore automatically complete amounts on an upstream progress claim?
- After Procore creates the progress claim, you can preview it as follows:
- Scroll to the Summary Preview area.
Tip
How does Procore calculate the 'Current Amount Due' value? To learn more, see How does Procore calculate a progress claim's 'Current Payment Due' amount? - Ensure the progress claim appears as expected.
- Scroll to the Summary Preview area.
Edit the Progress Claim Line Items on the Detail Tab
If your Procore user account has been granted the required user permissions for viewing the Detail tab, you can update the progress claim line items:
- Click the Detail tab.
- Click the Edit button.
- Enter data only in the YELLOW boxes:
- Work Completed: This Period
If you confirmed the option to automatically complete the owner progress claim's amounts. See How does Procore automatically complete amounts on an upstream progress claim?, the values from the 'Work Completed: This Period' column from any related subcontractor progress claims and any direct costs amounts are included in this column. - Materials Presently Stored
If you confirmed the option to automatically complete the owner progress claim's amounts. See How does Procore automatically complete amounts on an upstream progress claim?, the values from the 'Materials Presently Stored' column in any related subcontractor progress claims are included in this column. - Work Retention Retained this Period
Enter a percentage or dollar amount for work retention retained this period. You can also set retention on all line items by entering a value into the right sidebar and clicking Set. - Materials Retention Retained this Period
Enter a percentage or dollar amount for materials retention retained this period. You can also set retention on all line items by entering a value into the right sidebar and clicking Set. - Work Retention $ Released This Period
Enter a dollar amount of work retention released this period.
- Work Completed: This Period
- Scroll to the bottom of the progress claim and continue with the next step.
Add Approved Variations to the Progress Claim
If a variation is in the 'Approved' status and has line items that impact a progress claim, the system lists the variation in the 'Approved Head Contract Variations to Add to this Owner Progress Claim' table. If you want to add the variation to the progress claim now, follow these steps:
- Scroll to the bottom of the progress claim's Detail tab.
- Review the variation number, title and amount.
- Optional: In the Add to Owner Progress Claim As column, click the Add to Progress Claim button.
A GREEN banner confirms the progress claim was added successfully. - Continue with the next step.
Notes
The variation detail updates the appropriate line items on the progress claim. You have these options:
- To view the variation detail, follow the steps in Export an Owner Progress Claim. The PDF export file shows the Net Change by Variations value on line 2 and the Variation Summary table at the bottom of the Contractor's Application for Payment.
- To view the updates on the head contract, navigate to the head contract, click the General tab and scroll down to the Contract Summary Report.
- To change the level of detail showing on the head contract, see Edit the Advanced Settings on a Head Contract.
- The values from an owner progress claim are never copied to a variation.
Save the Progress Claim
To save your changes, click Save.