Objective

To add an entry to the Productivity section of the Site Diary using the Procore app on an Android mobile device.

Background

The Productivity section allows you to track how much material arrives on site and how much is installed. Any "Approved" subcontracts or purchase orders with the Unit/Quantity accounting method will appear here so you can track the installation against the line items in the contract.

Things to Consider

Steps

  1. Open the Procore app on an Android mobile device.
  2. Navigate to the project's Site Diary tool.
  3. Tap the date to select the calendar day for which you want to create a new entry.
  4. Tap icon-plus-quick-create-mobile2.png to create a new entry.
  5. Tap Productivity.
  6. Tap into the following fields to enter the relevant information:
    • Contract: Select the purchase order or commitment.
    • Line Item: Select the line item.
    • Quantity Delivered: Enter the amount.
    • Quantity Put-In-Place: Enter the amount.
  7. Tap Save.