Create a Payment Program from the Progress Billings Tool
Note

Objective
Background
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Commitments tool.
- Additional Information:
- Procore can automatically notify subcontractors by email when progress claims are approved. See Configure Settings: Progress Billings.
- You can define custom text which appears in the footer of payment program PDFs. See Configure Settings: Progress Billings.
Prerequisites
- The 'Display Subcontractor Claimed Amounts' option must be enabled in the project's Progress Billings tool’s configuration settings. See Configure Settings: Progress Billings.
- Complete the steps in Create a Progress Claim on Behalf of a Progress Claim Contact or Submit a New Progress Claim as a Progress Claim Contact.
- In order for amounts to appear on the payment program, subcontractors must enter amounts in the 'Work Completed This Period' and 'Materials Presently Stored' columns of the progress claim. See Submit a New Progress Claim as a Progress Claim Contact.
Steps
- Navigate to the project's Progress Billings tool.
- Click the Subcontractor tab.
- Click the commitment that you want to issue an progress claim for.
- Click the Progress Claims tab.
- Perform one of the following steps:
- Click the PDF icon
to the far right side of the most recent line item.
OR - Click View next to the most recent line item and then on the Progress Claims screen, select PDF from the Export drop-down list.
Example
- Click the PDF icon